Our steel simulations incorporate the layout and various equipments such as furnaces, de-sulphurization units, casters, cranes, transfer carts, maintenance and repair activities. By focusing on torpedo ladle logistics, crane logistics within the SMS and slag pot logistics in & out of the SMS, the simulations enable us to accurately analyze the following:
Heats per day |
Crane requirement & utilization |
Impact of crane interference on throughput |
Buffer stands, transfer carts & equipment relocation to minimize crane interference |
Hot metal and steel ladle requirement |
Impact of different grades on secondary processing & casting |
Impact of equipment and ladle maintenance on throughput |
Slag pot handling and slag pot carrier requirement |
Torpedo ladle and locomotive engine requirement |
Additional railway tracks & crossovers for efficient torpedo ladle movement |